摘要
分析了高填方地基处理中需主要解决的问题,包括有效加固深度和工后沉降的确定,并结合设计实践,分析了具体高填方强夯地基处理项目,探讨了强夯法在解决高填方地基承载力及工后沉降方面所具有的优势及需注意的事项。
The paper analyzes the main issues involved in high embankment foundation treatment, including the determination of the effective reinforcement depth and post- construction settlement, and studies a specific high embankment foundation treatment project using dynamic compaction method combining with design practice,and discusses the advantages and matters need attention using dynamic compaction method in high embankment foundation treatment.
出处
《煤炭工程》
北大核心
2015年第11期58-59,共2页
Coal Engineering
关键词
地基处理
强夯法
高填方
foundation treatment
dynamic compaction method
high embankment