摘要 南通电厂码头输煤通道需跨越天生港水道和横港沙,为减少输煤通道对天生港水道通航的影响,设计分别就输煤通道采用桥梁方案和隧道方案通过天生港水道进行了专题研究,通过对两种输煤通道方案的比较和分析,提出在现阶段实施桥梁方案的优越性。 The coal conveying channel of Nantong power plant terminal has to go across Tianshenggang waterway and Henggangsha shoal. In order to decrease the impact on the navigation of Tianshenggang waterway, monographic study is done respectively for the coal conveying channel passing Tianshenggang waterway by bridge or tunnel. The superiority of the bridge construction at the present stage is proved through the comparison and analysis of the above options for coal conveying channel.
出处 《港工技术》 2014年第4期16-20,共5页 Port Engineering Technology
关键词 输煤通道 桥梁 隧道 比较 coal conveying channel bridge tunnel comparison
  • 相关文献

参考文献4

  • 1中交第二航务工程勘察设计院有限公司.华能南通电厂三期直接输煤工程可行性研究报告(栈桥专题报告)[R].武汉:中交第二航务工程勘察设计院有限公司,2004. 被引量:1
  • 2GB50139-2004内河通航标准[S].北京:中国计划出版社.2004. 被引量:7
  • 3上海市隧道工程轨道交通设计研究院.华能南通电厂输煤隧道工程工程可行性研究报告[R].上海:上海市隧道工程轨道交通设计研究院,2003. 被引量:1
  • 4上海市隧道工程轨道交通设计研究院.南通天生港发电有限公司码头输煤隧道方案论证报告[R].上海:上海市隧道工程轨道交通设计研究院,2013. 被引量:1