大型粮库施工进度优化设计 被引量:1

CONSTRUCTION SCHEDULE OPTIMIZATION DESIGN OF LARGE GRAIN DEPOT
原文传递
导出
摘要 大型粮库的进度控制是政府主管部门、业主和施工单位面临的难题之一.关键链项目管理技术通过设置并监控缓冲区,减少不确定性因素对工程进度的影响.在分析大型粮库进度管理特点的基础上,引入工期折减系数和位置权数对缓冲区设置方法进行改进,综合考虑了工序的复杂程度、资源约束及管理者的风险偏好度等对工期的影响;并以某大型粮库进度控制为例进行了实证研究. Schedule control of large grain depot is one of the difficult problems for the competent department of government, the owner and construction companies. The critical chain project management technology can reduce delay of uncertainty factors on the schedule by setting and monitoring a buffer region. On the basis of analyzing the characteristics of large grain depot schedule management, a time reduction coefficient and a position weight were introduced to improve the buffer region setting manner, fully considering influences of the complexity of procedures, resource constraint,risk preference of managers and the like on the construction time;and the empirical study on schedule control was performed in a large grain depot.
出处 《河南工业大学学报(自然科学版)》 CAS 北大核心 2013年第4期74-77,共4页 Journal of Henan University of Technology:Natural Science Edition
基金 国家"十二五"科技支撑计划项目(2011BAD03B01) 河南省青年骨干教师资助项目(2010GGJS-083) 河南工业大学2011年研究生科技创新基金项目(11YJCX64)
关键词 大型粮库 关键链技术 进度优化 large grain depot critical chain technology schedule optimization
  • 相关文献

参考文献9

二级参考文献78

共引文献182

同被引文献4

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部