工程项目工期—成本—安全水平均衡优化研究 被引量:6

Study on time-cost-safety level trade-off of construction project
下载PDF
导出
摘要 目前工程项目安全性的相关研究中,缺乏对于工期、成本等目标与安全性之间联系及相互影响的考虑。针对这一不足,在分析每项工序持续时间、完工成本、保证性安全成本与安全水平之间关系的基础上,通过将安全性与系统可靠性理论相结合,得到工程项目的安全水平指数,并进一步将安全目标引入工期—成本优化模型,构建了工程项目工期—成本—安全水平均衡优化模型。最后结合一个工程项目实例,利用PSO算法对模型进行了求解,得到工期、成本与安全水平的一系列Pareto解,从而验证了模型的有效性与合理性及其在工程项目安全管理中的实用性。 Current studies on construction security seldom considered relationships and mutual influences between time,cost and other objectives and security.This paper analyzed relationships between duration,cost of completion,guarantee safety cost and safety level of each activity,and deduced safety level index of construction project by the combination of security and system reliability.Then it established a time-cost-safety level equilibrium optimization model through integrating the objective of safety level into time-cost trade-off model.At last,it achieved the Pareto solution of the model using PSO algorithm based on a real example,and demonstrate the effectiveness,rationality and practicality of the model in safety management of construction projects.
出处 《计算机应用研究》 CSCD 北大核心 2013年第1期78-81,共4页 Application Research of Computers
基金 国家自然科学基金资助项目(70871088)
关键词 工程项目 系统可靠性 安全水平 均衡优化 construction project system reliability safety level trade-off
  • 相关文献

参考文献19

  • 1MITROPOULOS P T, CUPIDO G. The role of production and team- work practices in construction safety: a cognitive model and an empi- rical ease study [ J ]. Journal of Safety Research, 2009,40 ( 4 ) : 265- 275. 被引量:1
  • 2CHENG C W, LEU S S, CHENG Ying-mei,et al. Applying data min- ing techniques to explore factors contributing to occupational injuries in Taiwan's construction industry[ J ],Accident Analysis and Pre- vention ,2012,48:214-222. 被引量:1
  • 3HINZE J,PEDERSEN C, FREDLEY J. Identifying root causes of construction injuries [ .[ ].. Journal of Construction Engineering and Management, 1998,124 ( 1 ) :67 .:71. 被引量:1
  • 4FANG Dong-ping, XIE Fang, HUANG Xin-yu. Factors analysis- based studies on construction workplace safety management in China [ J]. International Joumal of Project Management,2004,22( 1 ). 43-49. 被引量:1
  • 5YU Jie,LiU Yue. Prioritizing highway Safety impr0vement projects: a multi- criteria model and ease study with safetyAnalyst [ J ]. Safety Science ,2012,50 (4) : 1085-1092. 被引量:1
  • 6FUNG I W H, TAM V W Y, IX) T Y,et al. Developing a risk assess- ment model for Construction Safety[ J]. International Journal of Pro- iect Management,2010,28 ( 6 ) : 593- 600. 被引量:1
  • 7陆宁,廖向晖,王巍,冯娟,肖燕.建设项目安全成本率分析模型[J].西安建筑科技大学学报(自然科学版),2007,39(2):161-164. 被引量:16
  • 8AZARON A, MOGHADDAM R T. Multi-objective time-cost trade-off in dynamic PERT networks using an interactive approach E J]. Euro- pean Journal of Operational Research, 2007, 180 (3): 1186- 1200. : . 被引量:1
  • 9TABEGHIAN H R, TAHERI H. An application of randomized mini- mum cut to the project time/cost'trade0ff pmbiem[ J] .' Applied Ma- thematics and Computation ,2006,173 (2): 1200: i 207. 被引量:1
  • 10GHODSI R, SKANDARI M R, ALLAHVERDILO0 M, eta/. A new practical model to trade-off time,, ct, and quality of a project[ J!. Australian Journal of Basic and Applied Sciences,2009,3 (4) : 3741-3756. 被引量:1

二级参考文献33

共引文献129

同被引文献53

引证文献6

二级引证文献45

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部