期刊文献+

地下洞室群施工系统分析 被引量:9

SYSTEM ANALYSIS OF COSTRUCTION OF THE GROUP OF TUNNELS AND CAVERNS
下载PDF
导出
摘要 应用循环网络计算机模拟技术与网络计划技术CPM,系统地研究了地下洞室群施工过程,为在地下洞室群施工中合理选择组织方式和最佳机械设备配置方案、编制施工进度计划提供了定量分析方法。通过对实际工程的模拟计算分析表明该方法之可行性。 In this paper, with the aid of cyclic network simulation and CPM technique, the construction process of the group of tunnels and caverns has been studied systematically. The approach described in this paper provides a scientific and quantitative analyzing method of compiling the reasonable schedule of the construction of underground structure groups and choicing the reasonable alternative scheme of construction organization. The calculation and analysis of the construction of a underground power plant system shows that the method is quite practical.
出处 《天津大学学报》 EI CAS CSCD 1991年第S2期9-14,共6页 Journal of Tianjin University(Science and Technology)
关键词 地下洞室群 施工组织 循环网络 网络计划技术 计算机模拟 group of tunnels and caverns, construction organization, cyclic network, CPM, computer simulation
  • 相关文献

同被引文献43

引证文献9

二级引证文献87

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部