摘要
简要介绍了钢板脱碳机理以及影响脱碳的因素(加热温度、加热时间、加热炉内气氛)。分析实际生产中造成50Mn2V钢板脱碳的原因,提出了通过改变加热时空燃比、加热炉内压力,对加热工艺进行优化,合理安排生产组织,使50Mn2V钢板脱碳层超标问题得到解决。
The decarburization principle of the steel and influence factors(namely: heating temperature,holding time,the atmosphere within the furnace) were introduced.The decarburization reasons caused by actual production were analyzed,the heating process was optimized by changing the air-fuel ratio,furnace pressure,and reasonable arrangement for production organization,the excessive problems for decarburization layer of 50Mn2V steel is resolved.
出处
《热加工工艺》
CSCD
北大核心
2011年第18期195-197,共3页
Hot Working Technology
关键词
脱碳层
脱碳机理
加热温度
加热时间
生产组织
decarburized layer
decarburization principle
heating temperature
heating time