针对溧阳抽水蓄能电站工程C1标、C2标的施工方案,较全面系统地分析了土石方施工工程中的影响因素,以及各个方面相互联系和制约关系,进行了土石方调配平衡系统与道路运输系统等的综合优化,以寻求合理的土石方调配方案,达到快速、合理、经济施工之目的。
In allusion to the construction schemes of the bid-sections of CI and C2 of the construction of Liyang Pumped Storage Hydropower Station, the impact factors from the construction of the earth-rock work are systematically analyzed herein along with the study on the mutually associated and restricted relationships at all the aspects concerned, and then the comprehensive optimizations are made on both the balancing system for the allocation of the earth-rock work and the road transportation system, so as to obtain a reasonable earth-rock work allocation scheme and get the target of quick, reasonable and economic construction.