摘要
因线路施工验收规范、金具、导、地线产品国家标准、液压施工工艺规程等不同专业的规范标准版本更新时间不同,致使现阶段线路施工导、地线压接试验的实施和结果判定出现了一些新情况和问题。通过对导线压接试验具体工程案例的分析,基于现行规程规范对线路工程的液压压接试验有效实施及结果判定进行了一定分析和研究,并提出了相关建议。
Problems have emerged in crimping test due to codes and specification of specialized fields are update at different time such as construction acceptance code,state specification of fitting,conductor and grounding line,as well as hydraulic construction technique.Through analyzing case of crimping test,suggestions are proposed based on current codes and specification.
出处
《江西电力》
2010年第6期31-33,46,共4页
Jiangxi Electric Power
关键词
现行规程规范
压接试验
结果判定分析
current codes and specification
crimping test
result analysis