摘要
对某600 MW机组渣煤水系统的设计容量、进水量、溢流情况等进行了评估,提供了渣煤水系统水量平衡图并进行了水质分析,探讨了造成渣煤水溢流的原因并提供了解决建议,同时对渣煤水处理系统扩容和出水回用等方面提供了相关建议。
The design capacity,water inflow,and overflow of the slag and coal water system for the 600 MW unit were evaluated.The water analysis was carried out based on the water balance diagram of the system.And the reasons and solutions of slag and coal water overflow are explored.Furthermore,some recommendations are put forward for the expansion of slag and coal water treatment system and the reuse of wastewater.
出处
《浙江电力》
2011年第1期40-42,共3页
Zhejiang Electric Power
关键词
600MW
渣煤水
溢流
评估
600 MW
slag and coal water
overflow
evaluation