摘要
简要分析了代数法、图上法在计算流水施工工期时存在的不足,提出了用矩阵法计算流水施工工期的方法.设计并分析了计算用表,说明了计算步骤,并用实例进行了验证.
The shortcomings of calculating flow construction period with algebra method and project drawing method are briefly analyzed. Matrix method is put forward to calculate flow construction period, the calculation table is designed and analyzed ,the calculation process is stated, and the matrix method is validated by examples.
出处
《沈阳工程学院学报(自然科学版)》
2010年第1期27-28,46,共3页
Journal of Shenyang Institute of Engineering:Natural Science
关键词
矩阵
代数法
图上法
流水施工工期
matrix
algebra method
project drawing method
flow construction period