摘要
华能玉环电厂1000 MW超超临界机组的汽机调门运行方式改变后,机组协调控制系统也发生了相应变化。分析了汽机调门运行方式对机组节能的影响,并对2号机组在调门开度为50%和100%运行方式下的机组协调控制系统作了调整与优化,以期在不影响机组调节性能的情况下最大程度发挥西门子汽机的节能优势。
Corresponding changes to optimize CCS and effects of energy-economize are introduced in the paper after operation mode regulation in Yuhuan 1000 MW SUCC turbine. CCS debugging and optimization were deployed when main steam modulation valve was working at 50% or 100% in unit 2, in order to exert maximum ener- gy-economize on SIMENSE turbine. The conclusion and study points are proposed in the paper.
出处
《浙江电力》
2009年第B07期1-4,共4页
Zhejiang Electric Power