期刊文献+

石家庄市北二环跨红星街立交工程现浇连续箱梁施工技术 被引量:3

Construction Technology for Cast-in-place Continuous Box Beam of Interchange Project at 2nd North Ring Road Over-crossing Hongxing Street in Shijiazhuang
下载PDF
导出
摘要 预应力连续箱梁施工是石家庄市北二环跨红星街立交项目的重难点工程。在介绍桥梁工程总体施工方案的基础上,阐述了现浇连续箱梁施工技术,重点对支架搭设进行了计算与分析。 Prestressed continuous box beam construction is the key and difficult work of the Interchange Project at 2nd North Ring Road Over-crossing Hongxing Street in Shijiazhuang City. Based on an introduction of the general plan for the construction of the bridge, the paper describes in details the cast-in-place continuous box beam construction technology, and focuses on the calculation and analysis of the erection of the support frame.
作者 闫乾印
出处 《石家庄铁道学院学报》 2008年第2期109-111,118,共4页 Journal of Shijiazhuang Railway Institute
关键词 连续箱梁 支架 施工技术 continuous box beam support frame construction technique
  • 相关文献

参考文献3

  • 1路桥集团第一公路工程局主编..公路桥涵施工技术规范[M].北京:人民交通出版社,2000:529.
  • 2交通部公路科学研究所.JTGF80--2004公路工程质量检验评定标准[S].北京:人民交通出版社.2005. 被引量:1
  • 3郭东海,胡成.连续箱梁施工控制中几个问题的探讨[J].安徽建筑工业学院学报(自然科学版),2007,15(2):22-25. 被引量:4

二级参考文献3

共引文献3

同被引文献5

引证文献3

二级引证文献1