摘要
文章采用地表排水、整坡填缝、削方、抗滑桩、预应力锚索等多种工程措施对某铁路隧道滑坡进行了综合治理,对处治后的滑坡体进行了变形监测,并就监测数据进行了分析,得出了一些有益的结论。
A landslide of railroad tunnel was renovated with surface drainage,trimming slope and filling slot, cutting,slide-resistant pile and prestressed anchoring cable.A deformation monitoring was given for landslide mass after renovation, and then monitoring date was analyzed. Finally, some useful conclusions were elicited through these works.
出处
《企业技术开发》
2006年第4期56-57,67,共3页
Technological Development of Enterprise
关键词
隧道滑坡
抗滑桩
预应力锚索
变形监测
landslide of tunnel
slide-resistant pile
prestressed anchoring cable
deformation monitoring