摘要
在水电站厂房这样结构复杂的大型水工结构的温度应力计算中,大量的时间花费在前后处理程序的编制上。针对这种情况,提出了将大型通用有限元软件与温度应力计算主体程序两者相结合的方法,并成功地将其应用于某电站厂房的施工期及运行期温度应力场仿真分析中。
Calculating the thermal stress of complex larger hydraulic structure, such as hydropower plant, the preprocessor and postprocessor will take much time. Therefore a method of combining a well knows FEM software with the professional program is applied. This method has been successfully practiced during the construction simulation for a hydropower plant.
出处
《西北水力发电》
2006年第1期17-20,共4页
Journal of Northwest Hydroelectric Power
关键词
贯流式机组厂房
施工期
运行期
温度应力
仿真分析
Turbine Hydropower Plant
Construction Periods
Operating Periods
Thermal Stress Simulation Analysis