带运输和设置时间的无等待并行流水车间调度问题研究 被引量:13

No-wait Parallel Flowshop Scheduling with Transfer and Setup Times
原文传递
导出
摘要 研究了一类从无缝钢管生产作业中提炼出的新的并行流水车间调度问题.该问题具有工件无等待、工序之间存在运输时间、设备需要调整时间等特点.这些特点使得问题变得相当复杂.建立了大规模的混合整数规划模型,通过提出的变换方法简化和降低了模型的规模.针对此模型,提出并开发了适合此问题的遗传算法.通过实验比较六种规则调度方法及遗传算法的性能.计算结果表明,六种规则调度中最好的方法是SPT,而遗传算法调度的性能优于SPT. This paper considers a class of parallel flowshop scheduling problem, which is abstracted from the production of seamless steel pipe and characterized by no-wait, transfer times between operations, machine dependent setup times, etc. These characteristics complicate the problem. We formulate it as a large scale mixed integer programming model. We present a transform method to simplify and decrease the scale of the model. A problem specific genetic algorithm is then proposed. We test the performance of six rule scheduling methods and genetic algorithm. The test results show that SPT is the best one of the six rule scheduling methods and the genetic algorithm is better than SPT.
出处 《系统工程理论与实践》 EI CSCD 北大核心 2006年第1期18-25,共8页 Systems Engineering-Theory & Practice
基金 国家自然科学基金(7017103060274049)
关键词 并行流水车间调度 无等待 设备带调整时间 工件带运输时间 启发式算法 parallel flowshop scheduling no-wait policy machine-dependent setup times job with transfer times heuristic algorithm
  • 相关文献

参考文献11

  • 1Johnson S M.Optimal two-and three-stage production schedules[J].Naval Research Logistics Quarterly,1954,1:61 -68. 被引量:1
  • 2Graves S G.A review of production scheduling[J].Management Science,1981,29:646-675. 被引量:1
  • 3IntentiaChina.TPCO业务改进报告[R].天津:天津钢管公司,2000.. 被引量:1
  • 4李长穆等著..PMC管加工设备与技术[M].北京:冶金工业出版社,1993:158.
  • 5Pekny J F,Miller D L.Exact solution of the no-wait flowshop scheduling problem with a comparison to heuristic methods[J].Computers & Chemical Engineering,1991,15 (11):741-748. 被引量:1
  • 6Allahverdi A,Gupta J N D,Aldowaisan T.A review of scheduling research involving setup considerations[J].Omega,1999,27:219-239. 被引量:1
  • 7Koulamas C.The total tardiness problem:review and extensions[J].Operations Research,1994,12:1025-1041. 被引量:1
  • 8Gonzalez T,Sahni S.Flowshop and jobshop schedules:complexity and approximation[J].Operations Research,1978,26:36 -52. 被引量:1
  • 9李建祥..钢铁供应链生产计划与调度问题研究[D].东北大学,2004:
  • 10Armentano V A,Ronconi D P.Tabu search for total tardiness minimization in flowshop scheduling problems[J].Computers & Operations Research,1999,26:219-235. 被引量:1

同被引文献126

引证文献13

二级引证文献90

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部