摘要
针对天生桥二级水电站Ⅲ号引水隧洞工程的特点,采用自制的全断面针梁式钢模台车施工,介绍了钢模台车的性能,详细论述了钢模台车各道工序施工过程和操作方式,提出了在操作过程中出现问题的解决办法和防治措施.钢模台车的应用提高了施工效率,保证了施工质量.
In accordance with construction feature of the third water_intake tunnel in Tianshengqiao second_step hydropower station,self_made steel_mould stair vehicles of whole_cross needle bridge are adopted.The performance of steel_mould stair vehicles and its each construction process and operating patterns are discussed.Then the ways of solving problems in the course and preventive and management meatures are put forward.Its application improves construction efficiency and guarantee quality.
出处
《华北水利水电学院学报》
2005年第2期22-24,共3页
North China Institute of Water Conservancy and Hydroelectric Power
关键词
混凝土衬砌
全断面针梁式钢模台车
Ⅲ号引水隧洞
天生桥二级水电站
concrete lining
steel_mould stair vehicle of whole_cross needle bridge
No.3 water_intake tunnel
Tianshengqiao second_step hydropower station