摘要
针对广东连州电厂440t/h循环流化床锅炉配135MW汽轮发电机甩负荷时锅炉燃料系统、烟风系统、汽水系统等参数的变化进行理论分析与研究,结合循环流化床锅炉的自身特点,探讨其运行方式与控制方法,为该类型机组甩负荷及快速变化负荷提供一定的借鉴。
According to the load-rejection test of the 440 t/h CFB matching 135 MW turbo-generator in Lianzhou Power Plant, the variations in the conditions of fuel feeding, flue gas and steam water systems are theoretically analyzed and studied. The operation and controlling modes of CFB are discussed according to the characteristics of CFB, some guidelines are proposed for the load-rejection and fast changing load of the same type unit.