大型沉管隧道管段沉放施工技术 被引量:26

Techniques for sinking and jointing tube sections of a large immersed tube tunnel
下载PDF
导出
摘要 以上海外环沉管隧道管段沉放对接为例 ,介绍“双三角形”布置锚缆管段平面定位和双浮箱四点竖向吊沉系统及设备 ,简述管段沉放对接工艺流程及测量定位技术 。 Authors of this paper, taking the sinking and jointing of tube sections of the Shanghai Outer-Ring immersed tube tunnel as an example, introduce the plane orientation by the ”double-triangle” mooring system and the double-pontoon four-point vertical hoisting and sinking equipment, brief the process of sinking and jointing and the technique of location surveying, and finally analyze the difficulties encountered in the sinking and jointing of tube sections.
作者 潘永仁 丁美
出处 《现代隧道技术》 EI 2004年第5期1-5,11,共6页 Modern Tunnelling Technology
基金 上海市建设技术发展基金项目 (编号 2 0 0 0 0 112 )
关键词 沉管隧道 管段沉放与对接 施工技术 Immersed tube tunnel Sinking and jointing of tube sections Construction technique
  • 相关文献

参考文献1

  • 1[2]The Tunnel, published by φresundsbro Konsortiet, May,2001. 被引量:1

同被引文献512

引证文献26

二级引证文献684

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部