本文叙述了秦山核电厂一回路主要调试项目以及在预运行试验和初始启动试验阶段的实施情况。调试结果表明,系统已具备所要求的功能,运行参数达到了设计要求,能安全、可靠地配合反应堆冷却剂系统,满足各种工况的运行要求。
This paper describes the main commissioning items of the auxiliary process systems of Qinshan Nuclear Power Plant and practise during initial start-up and pre-operation tests. The results from the commissioning show that those systems have all required functions, operation parameters meet the design requirements. Qinshan Nuclear Power Plant can be safely and reliable operated in various operation modes.