摘要
希尼尔水库大坝为现浇混凝土面板砂砾石均质坝,根据料场砂砾料的物理力学性质指标试验结果,建立了砾石含量、干密度与相对密度三因素曲线,从而确定出施工控制指标.本工程竣工后运行情况良好.
The Xinier Reservoir Project has a homogenous sand-gravel dam with a cast-in-place concrete deck.A three-factor curve consisting of a gravel content ,dry density and relative density was established by testing physico-mechanical indexes of the sand-gravel materials from borrow areas to obtain necessary indexes for construction control.After completion of the project,the operation has showed very successful results.
出处
《水利水电技术》
CSCD
北大核心
2004年第6期33-34,36,共3页
Water Resources and Hydropower Engineering
关键词
砂砾料
相对密度
干密度
砾石含量
希尼尔大坝
sand-gravel material
relative density
dry density
gravel content
Xinier Dam