摘要
介绍了灰土挤密桩的施工程序,并对桩孔定位、桩孔成型、桩孔夯填等施工各步骤的施工技术进行了阐述,最后对提高土中含水量的方法、缩颈处理以及对邻近建筑物的影响等施工中的相关问题进行了探讨,从而达到消除桩间土的湿陷性,提高承载力的目的。
Construction program of lime-soil compaction pile is introduced.From site localization,hole building and other aspects practical construction technology is presented.In view of the measures to increase moisture of soil and treatment of method of necking and other questions encountered in construction discussion is made in order to improve the bearing capacity of pile.
出处
《山西建筑》
2007年第6期119-120,共2页
Shanxi Architecture
关键词
灰土挤密桩
桩孔定位
缩颈
承载力
lime-soil compaction pile
site localization
necking
bearing capacity