摘要
在岩溶地质条件下进行钻孔成桩施工时难免会遇到溶洞,溶洞问题处理的好坏对后期的桩孔施工成效以及成桩的质量有着决定性的作用。本文主要通过对岩溶地质区域下的钻孔桩遇到溶洞时的施工问题进行分析,结合工程施工建设相关技术,并针对冲击式钻孔桩施工技术中遇溶洞施工问题提出有效的工程解决措施,为相关工程建设提供一定的技术参考。
It is inevitable that the drilled pile construction under the karst geological condition will encounter the cavern, and the good or bad treatment of the cavern problem has a decisive role in the effectiveness of the later pile hole construction as well as the quality of the pile. This paper mainly analyzes the construction problems of drilled piles encountered with caverns under the karst geological region, combines the related technology of engineering construction, and proposes effective engineering solutions for the construction problems encountered with caverns in the percussive drilled piles construction technology, in order to provide technical references for the related engineering construction.
出处
《管理科学与工程》
2023年第6期865-870,共6页
Management Science and Engineering