m×n流水型排序问题关键零件法的改进 被引量:8

The improvement of key job method for m×n permutation schedule problems
下载PDF
导出
摘要 关键零件法用于解m×n流水型排序问题时存在两点不足:一是没有给出适用条件,影响了优化程度;二是没有确定优化程度,不知何时得到满意解.为了解决这些不足,改进后的关键零件法给出了近似最优解解法严格的适用条件、近似适用条件以及新的零件排序规则.改进的解法优化程度明显,非常接近最优解,而且可以判断距最优解最大的距离. The key job method for solving m×n permutation schedule problems has two defects.One is that the condition is not given, so it affects the optimal extent. The other is that the extent of optimal solution is not determined.The improved optimal solving method gives the conditions, near conditions and the new rules for scheduling, and is high degree optimal and more near the optimal result.
作者 于福 贾春玉
出处 《哈尔滨工业大学学报》 EI CAS CSCD 北大核心 2004年第6期848-850,共3页 Journal of Harbin Institute of Technology
关键词 流水型排序 关键零件法 近似最优解 改进解法 permutation schedule key work center method near optimal improvement method
  • 相关文献

参考文献5

  • 1JOHNSON S M. Optimal two-and three-stage production schedule with setup time included [ J ]. Naval Res Lo gist Quarter, 1954(1): 61 -68. 被引量:1
  • 2PALMER D S. Sequencing jobs through a multi-stage process in the minmum total time-a quick method of ob taining a near optimal [ J ]. Operation Research Quart, 1965(16): 101 -107. 被引量:1
  • 3GUPTA J N D. Heuristic algorithms for the exact solu tion of the three-machine scheduling problem. [ J] Management Science, 1972(16): 11 - 18. 被引量:1
  • 4马天超主编..机械工业企业生产管理学[M].北京:机械工业出版社,1986:357.
  • 5唐恒永,赵传立编著..排序引论[M].北京:科学出版社,2002:263.

同被引文献81

引证文献8

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部