龙首二级水电站枢纽泄水建筑物布置的试验研究 被引量:1

Experimental Studies on Escape works Layout of Longshou Secondary Project
下载PDF
导出
摘要 龙首二级水电站的泄水建筑物为岸边陡槽溢洪道和泄洪冲沙洞。泄水建筑物单宽流量大、水头高、流速大,并且下游消能区自然条件较差,高速水流的流态控制和消能防冲问题突出。本文介绍泄水建筑物布置方案及消能防冲问题的试验研究成果。 Escape works of Longshou Secondary project are composed of bank-run spillway and spillway-flushing tunnel. The discharge per unit width, head and velocity are big and natural condition at downstream energy dissipation area is poor. Problems of fluid state control of high-velocity flow and energy dissipation are prominent. In this paper, experimental result on the escape works layout and downstream energy dissipation are presented.
出处 《西北农业学报》 CAS CSCD 2003年第3期170-174,共5页 Acta Agriculturae Boreali-occidentalis Sinica
关键词 龙首二级水电站 泄水建筑物 布置 挑流消能 窄缝鼻坎 Escape works Trajectory bucket-type energy dissipation Slit-type buckets
  • 相关文献

参考文献5

  • 1倪汉根.高效消能[M].大连理工大学出版社,2000.10. 被引量:1
  • 2华东水利学院主编.水工设计手册[M].水利电力出版社,1987.. 被引量:1
  • 3武汉水电学院主编.水力计算手册[M].北京:水利出版社,1980.12. 被引量:1
  • 4陈椿忘.水工水力学论文集[C].水利电力出版社,1993.10. 被引量:1
  • 5西北水利科学研究所.龙首二级(西藏水)水电站枢纽整体水工试验报告[R].陕西杨凌:西北水利科学研究所,2002.5. 被引量:1

同被引文献14

  • 1蔡进军,蒋齐,张源润,王月玲,董立国,季波,李生宝.宁南山区典型旱作农耕地土壤特性分析[J].西北农业学报,2007,16(2):75-79. 被引量:6
  • 2刘润生.水力学[M].上海:上海交通大学出版社,1987.67. 被引量:10
  • 3Mulbry, W, Kebede-Westhead E Pizarro C etal. Recycling of manure nutrients: use of algal biomass from dairy manure treatment as a slow release fertilizer[J]. Bioresourc. Technol, 2005,96,451-458. 被引量:1
  • 4Jenssen P D . Potential use of constructed wetlands for wastewater treatment in northern environments[J].War. Sci. Technol., 1993,28(10):149-157. 被引量:1
  • 5Vymazal J. The useof sub-surface constructed wetlands for wastewater treatment in the Czech Republic: 10 years experience[J]. Ecol. Eng. ,2002,18(5) : 633-646. 被引量:1
  • 6Gearheart R A, Finney B A, Lang M, et al. A comparison of system planning, design an d sizing methodologies for free water surface constructed wetlands[A]. 6th International Conference on Wetland Systems for Water Pollution Control[C]. 1998. 被引量:1
  • 7Bounds H C, Collins J, Liu Z, et al. Effects of lengthwidth ratio and stress on rock-plant filter operation. Small Flow J, 1998,4(1) :4-14. 被引量:1
  • 8Chalk E, Wheale G. The root-zone process at Holt by Sewage Treatment Works[J]. JIWEM, 1989, 3:201 -207. 被引量:1
  • 9王久贤.白泥坑人工湿地水力学计算研究[J].广东水利水电,1997(6):50-52. 被引量:36
  • 10王薇,俞燕,王世和.人工湿地污水处理工艺与设计[J].城市环境与城市生态,2001,14(1):59-62. 被引量:119

引证文献1

二级引证文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部