摘要 伊朗ARAK(4× 32 5MW)电厂 ,选用了东方汽轮机厂生产的汽轮机。该机调节保安系统选用电液并存方式 ,即使用电调和液调 2套独立的控制系统。用 1个行程区间的任何一点为位置来代替 1个确定的行程 ,可不必花费很长的时间去找要求的行程位置 4 2 .7mm处。这样大大地提高了调节系统的调试效率 ;缩短了调节系统调试的工作时间。 The turbines manufactured by the Dongfang Turbine Manufacture have been used in ARAK Power Plant(4×325 MW)in Iran. The regulation protective system of the turbine adopts both electrical and hydraulic modes and consists of 2 independent control systems with electric and hydraulic regulation. 1 definite stroke position is substituted by any point within a range of 1 stroke, which has saved a long time to seek for a required stroke position at 42.7 mm. Thus the test efficiency of the regulation system can be greatly increased and the time for test and regulation of the system greatly shortened.
作者 王增建
出处 《电力建设》 北大核心 2003年第9期20-21,23,共3页 Electric Power Construction
关键词 汽轮机 液压调节系统 数字式电液调节系统 速度变动率 调试 turbine hydraulic regulation system speed variation rate regulation method
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部