围绕澄浪桥主桥钢箱拱肋拼装的支架、吊装、标高和轴线控制、预拱度的设置等施工内容进行了论述,就施工方案中涉及的相关问题进行了比较系统分析论证,并基于现场控制过程对系杆拱的施工细节给出了建议。
The steel box arch rib assembling and hoisting,elevation axis control,setting of pre arch construction content were discussed of Chenglang Bridge. Meanwhile,it analyzed systematically related issues involved in construction scheme,and based on the control process of the tied arch construction details are proposed.