期刊文献+

斜井井筒过断层的探索实践

Exploration Practice of Inclined Mine Shaft Through Fault
下载PDF
导出
摘要 龙煤集团七煤分公司新立煤矿目前正在进行四阶段2条井筒的延伸,1条为轨道下山,1条为回风下山。井田内部共有标志性断层:逆断层FD及正断层FE。轨道下山正处于过FD断层期间。FD断层落差约15 m,有严重破碎裂隙带。施工过程中注瑞米材料加固巷道轮廓线,架设U形钢支架施工。 Seven branch coal in Xinli coal mine of longmei group is currently conducting four-stage two shaft extension a to track down a back down the hill. Mine field within a total of iconic faults: FD and FE fault inverse fault. Track down the hill is in the FD during faults. FD fault throw around 15 m,there is a serious crush fracture zone. Remy in the construction material reinforcement tunnel contour,placing of U-steel frame construction.
作者 符向东
出处 《煤炭技术》 CAS 北大核心 2014年第6期97-98,共2页 Coal Technology
关键词 井筒 下山 断层 裂隙 瑞米材料 支架 izutsu shaft down fault crack remy material support
  • 相关文献

参考文献4

  • 1唐海,周义.煤矿掘进巷道断层识别[J].矿业工程研究,2009,24(4):47-50. 被引量:12
  • 2徐永圻主编..煤矿开采学[M].徐州:中国矿业大学出版社,1999:549.
  • 3陈洪冶,李立志,李雪梅主编..矿床学[M].北京:地质出版社,2007:247.
  • 4李景霞,张立新,周明杰主编..地质学实践教程[M].哈尔滨:哈尔滨地图出版社,2010:266.

二级参考文献10

共引文献11

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部