摘要
为了提高线路设计效率,保证设计的直观性和准确性,将基于CAD和GIS的场景构建技术结合起来,利用基于.NET反射机制下的工厂模式技术,形成CAD和GIS设计场景的联动及切换。通过双场景联动技术,实现了线路路径-平断面图联动功能及排塔联动功能,使排杆布线更加直观、平断面图的绘制更加科学。将CAD及GIS设计融入到架空输电线路设计中,使输电线路设计更加便捷,符合建设坚强智能电网的需要。
In order to improve line design' s efficiency and ensure design' s immediacy and accuracy,combined the scenarios building technology based on CAD and GIS,the CAD and GIS design scene's linkage and switch were formed by using factory pattern based on reflection mechanism of. NET technology. Through the double-scene linkage technology,line path and flat and sectional diagram' s linkage and rowing tower' s linkage were accomplished. The technology makes the rowing towers and wiring more intuitive and the flat and section drawing more scientific. The design of CAD and GIS integrated into the design of overhead transmission line makes the design of transmission line easier,which meet the need of building strong smart grid.
出处
《建筑结构》
CSCD
北大核心
2016年第S1期1009-1012,共4页
Building Structure
基金
国家电网公司科技项目(GC71-13-042)