摘要
三峡左岸电站为坝后引水式厂房 ,共有 1 4台机组 ,单机容量 70 0MW ,总装机容量 980 0MW ,确保左岸电站按期投产将产生巨大的经济效益。三峡左岸电站厂房规模宏大 ,施工工序繁杂 ,要求的施工工期紧张 ,切实做好施工设计 ,是保障其有序施工和按期投产的先决条件。 2 0 0 0年底左岸电站实际施工进度较原设计进度略有滞后 ,为此设计部门提出了加快施工进度的措施 ,在建设各方的努力下工程进展顺利 ,预计在 2 0 0 3年将能顺利实现左岸电站第
The left bank powerhouse of TGP is a dam toe one, with 14 generator units, each with 700 MW and total capacity of 9800 MW. The commissioning of the left bank station on schedule will bring about great economic benefit. The TGP's left bank powerhouse characterizes large scale, complicated construction procedure and intense construction period, so the deliberate construction design is a prerequisite condition to guarantee that the construction proceeds smoothly and the power house be put into operation on schedule. Up to the end of 2000, the construction progress of the left bank powerhouse was slightly behind the designed schedule, therefore, the design department suggested some measures to speed up the construction progress. With the effort of all aspects, the construction proceeds smoothly, it is predicted that the object of the first generator unit's commissioning in 2003 can be reached successfully.
出处
《人民长江》
北大核心
2002年第12期1-2,共2页
Yangtze River
关键词
施工进度
坝后引水式厂房
三峡水利枢纽
设计
construction progress
construction plan
water intake powerhouse at dam toe
left bank power house
TGP