介绍了菏泽发电厂二期工程保安电源接线的设计思路和柴油发电机组具备带保安负荷条件后负荷的分批投入顺序 ,对设计的优缺点进行了分析 ,并提出了保安电源微机切换装置的设想方案。
This paper briefed the emergency power design principle of Heze Power Plant Phase II Project and introduced the load energizing sequence when the diesel-generator was ready to supply power. Advantages and disadvantages were analyzed and a microprocessor-based transfer device was proposed.