摘要
分析了湖北省500/220kV电磁环网的形成与发展,阐述了500/220kV电磁环网中220kV线路运行状况和存在的问题,以及电磁环网运行存在的安全隐患,主要从电网规划角度探讨了电磁环网解环的时间和解环地点。
This article analyzed the development of the electromagnetic loop network in Hubei province.the state and problems and safety hidden trouble in the electromagnetic loop network was descripted.At the view point of power system layout,an advice on when and where to break out the electromagnetic loop network was also given.
出处
《华中电力》
2002年第6期15-17,66,共4页
Central China Electric Power
关键词
2005年
湖北
电网
电磁环网
电力系统
输电线路
electromagnetic loop network
operation safety
system layout
break out loop