以上海某在产炼钢厂增建300 t LF炉工程桩基设计及其施工实践为例,探讨了在受到拟建场地环境狭小、工程地质条件差、桩基施工对在产厂房结构产生不利影响等特定条件下桩基设计及施工应重视的问题,可供类似工程项目借鉴。
A 300 t LF furnace is added for a steel works in production in Shanghai. The project is taken as an example to discuss the problems of the design and construction of pile foundations which should be taken into account in special conditions in the technical-transformation project. The special conditions include the narrow space in site,the bad soil conditions,and the bad influence of pile construction to the structure of main workshop. The research could be a reference for similar projects.