基于位置管理系统的施工进度计划应用研究

Research on Application of Construction Schedule Based on Location Management System
下载PDF
导出
摘要 传统关键路径法(CPM)在连续生产流及其相应资源配置管理方面存在不足。基于位置的管理系统(LBMS)能够弥补此类缺点。本研究实际应用自主研发的基于位置管理工具对关键路径法计划进行分析,并优化生产计划。研究结果显示,LBMS可在不影响项目持续时间的情况下,建立连续工作流程、平衡生产速率、优化资源配置。优化后的LBMS计划要素较少,其流线图效果简洁直观,利于生产各方沟通。 The traditional planning method,the Critical Path Method(CPM)is deficient in the management of continuous production flow and resource allocation.Location-based management system(LBMS) can compensate for such deficiencies.Based on actual project cases,this paper analyzed and improved CPM schedule by applying LBMS with the authors' independent development.The result of the study showed that LBMS could establish continuous workflows,balance production rate,optimize resources allocation without much interruptions or affecting project duration.Furthermore,LBMS schedules were optimized with fewer planning elements,hence its flowline graph had a concise and intuitive effect,facilitated communication among all parties.
作者 汤居庭 谢洪栋 王广兴 彭国平 Tang Juting;Xie Hongdong;Wang Guangxing;Peng Guoping(Ruison Lean Construction Co.,Ltd.,Jinan 250000,China)
出处 《土木建筑工程信息技术》 2024年第3期41-45,共5页 Journal of Information Technology in Civil Engineering and Architecture
基金 山东省工信厅企业技术创新项目(编号:202350101848)。
关键词 关键路径 基于位置管理 工作流程 资源配置 Critical Path Method Location-based Management System Workflow Resource Allocation
  • 相关文献

参考文献5

二级参考文献15

  • 1Fan S, Tserng H. Object-Oriented scheduling for repetitiveprojects with soft logics [ J ]. Journal of Construction Engineering and management, 2006, 132 (1) : 35-48. 被引量:1
  • 2Hegazy T, Kamarah E. Efficient repetitive scheduling for High-Rise construction [ J ]. Journal of Construction Engineering and Management, 2008, 134 (4) : 253-264. 被引量:1
  • 3Mattila K Abraham. Resource leveling of linear schedules using integer linear programming [ J ]. Journal of Construction Engineering and Management, 1998, 124 (3) : 232-244. 被引量:1
  • 4Hegazy T, Wassef N. Cost optimization in projects with repetitive non-serial activities [ J]. Journal of Construction Engineering and Management, 2001, 127 (3) : 183-191. 被引量:1
  • 5Arditi D, Tokdemir O B, Suh K. Challenges in Line-of- Balance scheduling [ J ]. Journal of Construction Engineering and Management, 2002 (12): 545-556. 被引量:1
  • 6Ammar M. Float analysis of [J]. Journal of Construction 2003, 21 (5): 535-542. 被引量:1
  • 7non-serial repetitive activities Management and Economics, Lucko G. Productivity scheduling method compared to linear and repetitive project scheduling methods [ J ]. Journal of Construction Engine ering and Management, 2008, 134 (9): 711-720. 被引量:1
  • 8满庆鹏,王要武.基于平衡线的施工管理方法在施工中应用[J].建筑管理现代化,2008,22(2):54-56. 被引量:1
  • 9任振,沈敏圣,王成程,张林,陈立华.改进挣值法在大型科研项目进度—成本管理的应用[J].科技管理研究,2016,36(20):211-214. 被引量:20
  • 10王静,曾莎洁,琚娟.资源受限项目调度模型的施工进度管理[J].同济大学学报(自然科学版),2017,45(10):1561-1568. 被引量:9

共引文献23

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部