摘要
为探究全地埋式污水处理厂的渗水风险及防治措施,首先对全地埋式污水处理厂的特点、本项目的地质条件和地下水位高等进行了分析,其次分析了地表水和地下水在暴雨季节向处理厂区渗漏的风险,最后结合污水处理厂的工程特点和渗水风险分析,从基坑的施工阶段防水、污水处理池的内壁防腐防水、地下室箱体顶板防水和变形缝施工处理等角度提出了污水处理厂渗水的防治处理措施。
In order to explore the seepage risk and prevention measures of the whole buried sewage treatment plant,the characteristics of the whole buried sewage treatment plant,the geological conditions and the high groundwater level ofthe project were analyzed firstly.Secondly,the risk of leakage of surface water and groundwater to the treatment plant during the rainstorm season was analyzed.Finally,the engineering characteristics and seepage risk ofthe sewage treatment plant were analyzed.The prevention and treatment measures of water seepage in sewage treatment plant are put forward from the aspects of waterproofing in construction stage of foundation pit,anticorrosion and waterproofing of inner wall of sewage treatment tank,waterproofing ofroof ofbasement box and construction treatment of deformation joint.
作者
汪浩
谭一夫
游云鹏
刘依林
方涛
WANG Hao;TAN Yi-fu;YOU Yun-peng;LIU Yi-lin;FANG Tao(China Railway Shanghai Engineering Bureau Group South China Municipal Construction Co.Ltd.,Guangzhou 510700,China)
出处
《工程建设与设计》
2024年第6期188-190,共3页
Construction & Design for Engineering
关键词
污水处理厂
全地埋式
渗水风险分析
防治措施
防水工程
sewage treatment plant all-buried
seepage risk analysis
prevention and control measures
waterproofing works