摘要
传统岩板安装方式的弊端制约了岩板的发展,超大规格岩板安装更是装饰行业内的一道难题。论文以北京市国家会议中心二期项目中首层大堂墙面超大规格岩板作为研究对象,对超大规格墙面岩板干挂安装的工艺流程及操作要点进行详细阐述,较为全面地概括了整个施工过程中工程质量的控制、安全环保措施等内容。
The disadvantages of the traditional installation mode of rock plate restricts the development of rock plate,and the installation of oversized rock plate is a difficult problem in the decoration industry. In this paper, oversized rock slab on the lobby wall of the first floor of Beijing National Convention Center Phase II project is taken as the research object, and the technological process and operating points of dry-hanging installation of oversized rock slab on the wall are elaborated. Finally, the project quality control, safety and environmental protection measures in the whole construction process are comprehensively summarized.
作者
申洋洋
祝岗
尤佳
范丹岚
SHEN Yang-yang;ZHU Gang;YOU Jia;FAN Dan-lan(China Construction Second Bureau Decoration Engineering Co.Ltd.,Beijing 100000,China)
出处
《工程建设与设计》
2023年第19期6-9,共4页
Construction & Design for Engineering
关键词
超大规格岩板
干挂安装
工艺流程
建筑装饰
large size rock plate
dry mounting
process flow
architectural decoration