期刊文献+

基于BIM的岩溶区预成孔管桩施工方法研究

Study on Construction Method of Preformed Pipe Pile in Karst Area Based on BIM
下载PDF
导出
摘要 通过BIM技术模拟管桩在溶洞地质中不同位置情况,采用引孔沉桩法施工预制管桩以解决管桩的施工问题,然后采用长螺旋引孔和潜孔锤破岩施工技术和带锯齿状桩靴和预制的高强混凝土薄壁钢管桩施工技术解决溶洞地质中岩面不平整导致的桩端滑移、断桩问题,提高成桩的质量和确保基础的安全。 The BIM technology is used to simulate the different positions of pipe piles in the karst cave geology.The prefabricated pipe piles are constructed by the method of leading hole and sinking piles to solve the construction problems of pipe piles.Then the long spiral leading hole and down the hole hammer rock breaking construction technology and the construction technology of high-strength concrete thin-walled steel pipe piles with serrated pile shoes and prefabrication are used to solve the problems of pile tip sliding and pile breaking caused by the uneven rock surface in the karst cave geology,improve the quality of pile formation and ensure the safety of the foundation.
作者 钟颖思 邵泉 冯伟 ZHONG Ying-si;SHAO Quan;FENG Wei(Guangzhou 2nd Construction Engineering Co.,Ltd.,Guangzhou 510045;Guangzhou Municipal Construction Croup Co.,Ltd.,Guangzhou 510030;Guangzhou Construction Co.,Ltd.,Guangzhou 510030)
出处 《广州建筑》 2023年第3期37-40,共4页 GUANGZHOU ARCHITECTURE
基金 广州市建筑集团有限公司科技计划项目(2021-KJ029)。
关键词 引孔沉桩法 长螺旋钻孔桩 潜孔锤 锯齿状桩靴 pilot hole pile sinking long auger bored pile hammered pile serrated pile shoe
  • 相关文献

参考文献10

二级参考文献47

共引文献25

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部