摘要
随着BIM技术的发展,给排水构筑物设计不断尝试把BIM技术运用到实践中。萧山钱江污水处理厂四期扩建工程位于浙江省杭州市萧山钱江农场,设计规模40万m^(3)/d,是一座半地下箱体式污水处理厂。结构设计人员就Revit软件中建立的三维模型,结合YJK软件,探索地下厂构筑物结构计算,证明了地下厂项目利用三维模型整体计算的可能性。
With the development of BIM technology,the design of water supply and drainage structures is trying to apply BIM technology into the practice.The Xiaoshan Qianjiang Wastewater Treatment Plant Phase IV Extension Project is located in Xiaoshan Qianjiang Farm,Hangzhou City,Zhejiang Province.Its design scale is 400000 m^(3)/d.and it is a semi-underground box-type wastewater treatment plant(WWTP).Revit software is used to establish a three-dimensional model.Combined with YJK software,the structural calculation of underground WWPT structures is explored to prove the possibility of using the three-dimensional model for overall calculation of underground WWTP projects.
出处
《城市道桥与防洪》
2023年第7期252-257,M0022,共7页
Urban Roads Bridges & Flood Control
基金
上海市政工程设计研究总院(集团)有限公司项目,地下污水处理厂抗震关键技术研究(K2019K072)。
关键词
BIM
REVIT
YJK
地下污水厂
结构计算
BIM
Revit
YJK
underground wastewater treatment plant(WWTP)
structural calculation