深部高应力软岩巷道底鼓机理及防治对策 被引量:1

Mechanism and Prevention Measures of Heaving Floor in Deep High Stress Soft Rock Roadways
下载PDF
导出
摘要 为控制深部软岩巷道变形,保证安全生产,针对矿井深部地应力增加、软岩底板发生流变与结构失稳、收敛变形严重等情况,提出锚网+锚索联合支护底板治理方案,在轨枕中间加设锚杆,在底板中部加设锚索和锚网,并架设梯子梁,实现巷道断面的整体支撑结构。工程应用表明:巷道修护50 d后,巷道底鼓变形速度趋于0.01 mm/d。 In order to control the deformation of deep soft rock roadway and ensure safe production,in view of the increase of deep crustal stress in mine,rheological and structural instability of soft rock floor,serious convergence deformation and other situations,a floor administer scheme of anchor mesh+anchor cable combined support is proposed,with anchor bolts added in the middle of sleepers,anchor cables and anchor nets added in the middle of the floor,and ladder beams erected to achieve the overall support structure of the roadway section.Engineering applications showed that after 50 days of roadway maintenance,the deformation rate of the roadway heaving floor tends to 0.01 mm/d.
作者 胡加振 Hu Jiazhen(Henan Province Xuchang Xinlong Mining Industry Co.,Ltd.,Liangbei Coal Mine,Henan Xuchang 461000)
出处 《山东煤炭科技》 2023年第7期65-67,共3页 Shandong Coal Science and Technology
关键词 软岩 巷道 底鼓 治理 soft rock roadway heaving floor administer
  • 相关文献

参考文献6

二级参考文献76

共引文献411

同被引文献3

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部