延迟焦化装置节能优化措施

Energy-saving optimization measures of delayed coking unit
下载PDF
导出
摘要 对盘锦浩业化工有限公司100万t/a延迟焦化装置进行了能耗分析,并从余热利用和设备改造的角度提出了节能优化措施。结果表明:通过采取焦化柴油与溶剂再生塔热联合,焦化产品热出料,高温管道保温优化,富气压缩机改为电驱动的节能优化措施后,可节省水1223.447 t/h,蒸汽10.753 t/h,燃料气21.4 m^(3)/h,CO_(2)减排量可达3.36万t/a。 The energy consumption of 1 Mt/a delayed coking unit of Panjin Haoye Chemical Co Ltd was analyzed,and energy-saving optimization measures were proposed from the perspective of waste heat utilization and equipment transformation.The results showed that by adopting the thermal combination of coking diesel and solvent regeneration tower,the thermal discharge of coking products,the optimization of high-temperature pipeline insulation and the energy-saving optimization measures of replacing the rich gas compressor with electric drive,the water,steam and fuel gas could be saved by 1223.447 t/h,10.753 t/h,21.4 m^(3)/h,and the CO_(2)emission reduction could reach 33.6 kt/a.
作者 常慧亮 贾海龙 夏明礼 CHANG Hui-liang;JIA Hai-long;XIA Ming-li(Panjin Haoye Chemical Co Ltd,Panjin 124000,China)
出处 《石化技术与应用》 CAS 2023年第4期303-306,共4页 Petrochemical Technology & Application
关键词 延迟焦化装置 节能 优化 CO_(2)减排 delayed coking unit energy-saving optimization CO_(2)emission reduction
  • 相关文献

参考文献4

二级参考文献7

共引文献18

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部