摘要
以早期人防洞隧道为依托,阐述了早期人防洞隧道围岩变形监控量测工作的目的、方法及测点布设原则。根据早期人防洞的工程特点开发了一套变形监测系统,并通过数据收集、数据传输及数据分析三个方面对监测系统的架构进行了具体阐述。最后通过工程实例验证监测系统的可靠性,解决了早期人防工程隧道围岩变形测量难题,为今后类似工程监测提供了借鉴。
Based on the early civil air defense tunnel,the purpose,method and measuring point layout principle of surrounding rock deformation monitoring and measurement in it was expounded.According to its engineering characteristics,a deformation monitoring system was developed,and the architecture of the monitoring system was described in detail from three aspects of data collection,data transmission and data analysis.Its reliability was verified by engineering examples.The problem of surrounding rock deformation measurement in early civil air defense tunnel is solved,which provides reference for future similar engineering monitoring.
作者
李雷
陶其梅格
陈超
LI Lei;TAO Qimeige;CHEN Chao(Qinghai Civil Air Defense Engineering Design and Research Institute Co.,Ltd.,Xining 810000,China;State Key Laboratory for Geomechanics and Deep Underground Engineering,China University of Mining&Technology,Xuzhou 221116,China)
出处
《城市勘测》
2023年第2期205-208,共4页
Urban Geotechnical Investigation & Surveying
基金
青海省中央引导地方科技发展资金计划项目(2021ZY018)
江苏省高等学校自然科学研究项目资助(20KJA560003)。
关键词
早期人防洞
隧道
围岩变形
监控量测
监测系统
early air defense cave
tunnel
surrounding rock deformation
monitoring and measurement
monitoring system