摘要
建筑深基坑土方开挖被视为整个项目中易发生安全事故的环节之一,若不做好预防工作,严格落实施工过程中的安全控制工作,将可能引发滑坡、坍塌、构筑物破坏等重大事故。文章以荆州煤炭铁水联运储配基地一期翻车机房项目为例,对其深基坑土方开挖方法展开详细介绍,深入研究了开挖施工中的排水控制、边坡防护控制措施等内容,以减少事故发生的可能性,有效确保施工全过程的安全。
The earthwork excavation of building deep foundation pit is regarded as one of the links prone to safety accidents in the whole project.If the prevention work is not done well and the safety control work in the construction process is not strictly implemented,major accidents such as landslide,collapse and structure damage may be caused.Taking the first phase of dumper room project of Jingzhou coal-iron-water combined transportation storage and distribution base as an example,this paper introduces the earthwork excavation method of deep foundation pit in detail,and deeply studies the drainage control and slope protection control measures in excavation construction,so as to reduce the possibility of accidents and effectively ensure the safety of the whole construction process.
作者
吴广
WU Guang(No.5 Engineering Company of CCCC First Harbor Engineering Co.,Ltd.,Qinhuangdao 066002,Hebei,China)
出处
《工程技术研究》
2023年第4期136-138,共3页
Engineering and Technological Research
关键词
深基坑
开挖
安全控制
deep foundation pit
excavation
safety control