摘要
为优化建筑施工深基坑支护效果,要落实全过程管理机制,提升具体环节管理水平,依据标准化控制工作要求落实管理内容,从而提高建筑施工基坑支护方案的安全性。文章结合具体工程案例对建筑深基坑支护施工管理的具体内容展开讨论,首先简要介绍了整体施工方案,然后从工程桩和支护桩施工、止水桩施工、管井和降排水施工、钢筋混凝土梁支撑及土方工程挖运环节的施工管理要点进行探讨,最后提出了相关施工管理建议,以供参考。
In order to optimize the effect of deep foundation pit support in building construction,it is necessary to implement the whole process management mechanism,improve the management level of specific links,and implement the management content according to the requirements of standardized control work,so as to improve the safety of foundation pit support scheme in building construction.This paper discusses the specific content of construction management of deep foundation pit support in combination with specific engineering cases.Firstly,it briefly introduces the overall construction scheme,then discusses the key points of construction management from the aspects of engineering pile and support pile construction,water stop pile construction,pipe well and drainage construction,reinforced concrete beam support and earthwork excavation and transportation links,and finally puts forward relevant construction management suggestions for reference.
作者
韩磊
HAN Lei(China Geo-engineering Corporation,Beijing 100093,China)
出处
《工程技术研究》
2022年第24期119-121,共3页
Engineering and Technological Research
关键词
深基坑
支护桩
止水桩
施工管理
建筑工程
deep foundation pit
support pile
water stop pile
construction management
building engineering