摘要
结合实际工程案例,对泵站水力模型建立及校核两个过程进行分析,总结了水力建模所需参数及参数获取方式,明确了校核过程所需监测数据,提出了模型关键校核步骤。校核后,该泵站稳态水力模型在4种工况下的模拟值偏差均低于5%,瞬态水力模型在2种工况下的模拟值偏差均低于3.5%。
Combined with the actual engineering cases,this paper analyzes the two processes of hydraulic model establishment and calibration of the pumping station,summarizes the parameters required for hydraulic modeling and the method of obtaining parameters,clarifies the monitoring data required for the verification process,and proposes the key verification steps of the model.After the verification,the simulated value deviation of the steady-state hydraulic model of the pump station is less than 5%under the four working conditions,and the deviation of the simulated value of the transient hydraulic model under the two working conditions is less than 3.5%.
作者
孙石雨
郭芳
陈永
王国田
李久义
蒋丽云
王加禄
SUN Shiyu;GUO Fang;CHEN Yong;WANG Guotian;LI Jiuyi;JIANG Liyun;WANG Jialu(School of Civil Engineering,Beijing Jiaotong University,Beijing 100044,China;YaTai Construction Science&Technology Consulting Institute Co.,Ltd.,Beijing 100120,China;Zhuzhou Southern Valve Co.,Ltd.,Zhuzhou 412000,China)
出处
《给水排水》
CSCD
北大核心
2022年第12期131-137,共7页
Water & Wastewater Engineering
关键词
市政泵站
水力模型
模型校核
水锤
压力监测
Municipal pump station
Hydraulic model
Model check
Water hammer
Pressure monitoring