2020年春节期间,为应对新冠肺炎疫情,上海市政府在位于金山区的上海市公共卫生中心医院内迅速启动了应急救治临时医疗用房项目的建设。在各方的共同努力下,仅用时近20天就完成了200床的负压隔离病房的设计和建设工作,为战胜疫情,保障上海的城市安全起到了重要的作用。
During the Spring Festival of 2020,in response to the COVID-19 outbreak,the Shanghai Municipal Government has quickly launched the construction of a temporary medical housing project for emergency treatment in the Shanghai Public Health Center Hospital located in Jinshan District.With the joint efforts of all parties,the design and construction of a 200-bed negative pressure isolation ward has been completed within only 20 days,which plays an important role in overcoming the epidemic and ensuring the safety of Shanghai.