安全注入系统与安全壳喷淋系统早期互为备用事故策略研究 被引量:1

Study on the Accident Strategies for the Mutual Standby of the Safety Injection System and Containment Spray System in the Early Stage
下载PDF
导出
摘要 在大部分CPR1000堆型核电厂中,安全注入系统(RIS)和安全壳喷淋系统(EAS)的互为备用仅应用于大LOCA(Lossofcoolantaccident)事故工况后15天。阳江核电厂5号、6号机组进行了H4管线(安全注入系统和安全壳喷淋系统互为备用的连接管线)改进,将安全注入系统和安全壳喷淋系统的互为备用也可应用于中、小LOCA事故的早期工况。本文研究RIS系统和EAS系统早期互为备用在状态导向法事故运行程序SOP(StateOrientedProcedure)中的应用,结合基于H4管线改进的现实性事故分析,设计出中、小LOCA叠加H4工况(低压安注泵全部失去或喷淋泵全部失去)事故处理的策略及手段。 The mutual standby of the safety injection system and the containment spray system is applicable to the large LOCA accident after 15 days in CPR1000 nuclear power plant. The H4 pipeline(The mutual standby connecting line between the safety injection system and the containment spray system) modification is introduced in the Unit 5 & 6 of Yangjiang NPP.And the mutual standby of the safety injection system and the containment spray system is applicable to the accident medium or small LOCA in the early stage condition. The study on the application of mutual standby of the safety injection system and the containment spray system in the early stage of the state oriented procedure(SOP) is based on the realistic accident analysis of H4 pipeline modification. The SOP strategies and mean s of medium or small LOCA accumulated H4 condition(The total loss of low pressure safety injection pumps or containment spray pumps) in the early stage condition are designed.
作者 吴广君 王超 李龙 梅亮 杨自军 WU Guangjun;WANG Chao;LI Long;MEI Liang;YANG Zijun(Suzhou nuclear power research institute,Shenzhen of Guangdong Prov.,518000,China)
出处 《核科学与工程》 CAS CSCD 北大核心 2022年第2期436-442,共7页 Nuclear Science and Engineering
关键词 核电厂 安全注入系统 安全壳喷淋系统 早期 互为备用 Nuclear power plant RIS EAS Mutual standby State oriented Early stage condition
  • 相关文献

参考文献8

二级参考文献23

  • 1孙吉良,肖岷,黄辉章,杨玲,熊春华.大亚湾核电站严重事故管理导则[J].核动力工程,2003,24(S2):5-8. 被引量:9
  • 2贺禹,苏林森.900MW压水堆核电站系统与设备[M]北京:原子能出版社,2004. 被引量:2
  • 3谭建生.核电相关法律法规汇编(上卷):中国核电相关法律法规汇编[M]北京:法律出版社,2009. 被引量:1
  • 4NRC.Acceptance criteria for emergency corecooling systems for light water nuclear power re-actors,Appendix K,ECCS evaluation models[S].US:NRC,1992. 被引量:1
  • 5LIANG K S,CHANG C J,HUANG H J.De-velopment of LOCA licensing calculation capabili-ty with RELAP5-3Din accordance with Appen-dix K of 10CFR50.46[J].Nuclear Engineeringand Design,2002,211:69-84. 被引量:1
  • 6American Nuclear Society.Proposed ANS stand-ard:Decay energy release rates following shut-down of uranium-fueled thermal reactors[S].USA:American Nuclear Society,1971. 被引量:1
  • 7YODER G L.Dispersed flow film boiling in rodbundle geometry-steady state heat transfer dataand correlation comparisons[G].USA:OakRidge National Laboratory,1982. 被引量:1
  • 8ERICKSON L.The Marviken full-scale criticalflow tests interim report:Results from test 22,MX3-87[R].Sweden:Studsvik Eco&SafetyAB,1979. 被引量:1
  • 9CATHCART J V,PAWEL R E,McKEE R A,et al.Zirconium metal-water oxidation kineticsⅣreaction rate studies,ORNL/NUREG-17[R].USA:ORNL,1977. 被引量:1
  • 10BAKER L,Jr,JUST L C.Studies of metal-wa-ter reactions at high temperatures,ANL-6548[R].USA:ANL,1962. 被引量:1