摘要
阐述了优化后的帷幕灌浆工艺特点,为了尽量减少在工期紧的情况下大坝整体填筑与帷幕灌浆相互交叉的被动局面,对常规的帷幕灌浆工艺进行了优化,最大限度地减少了人员和机械窝工,使灌浆能够连续进行,做到了提前完成灌浆,同时也使大坝填筑进度加快。
Expounds the characteristics of the optimized curtain grouting process.In order to minimize the passive situation of the intersection between the overall dam filling and curtain grouting under the tight construction period,the conventional curtain grouting process was optimized to reduce personnel and mechanical idling,so that the grouting can be carried out continuously and be completed ahead of time.At the same time,it also speeds up the dam filling progress.
出处
《山西水利科技》
2022年第1期8-10,13,共4页
Shanxi Hydrotechnics
关键词
工期紧
工艺流程
基岩段
接触段
tight construction period
technological process
bedrock section
contact section