摘要
分析东北某地标性项目从供电局引入1期的供电量、1期实际用电量、3期负荷估算及由1期供电给3期的供电距离进行可行性研究,決出利用改造原1期高压供电设施的负载率以降低扩建部分的初装成本,并提出跟进事项。
A feasibility study is carried out for the power supply volume of Phase 1,actual electricity consumption of Phase 1,load estimation of Phase 3 and the power supply distance from Phase 1 to Phase 3 introduced from the power supply bureau of a landmark project in Northeast China.The load rate of the high-voltage power supply facility of existing Phase 1 is used to reduce the cost for initial installation of the extension part and follow‑up matters are proposed.
作者
吴华杰
WU Huajie(WSP(Asia)Limited,Hong Kong,China)
出处
《建筑电气》
2022年第3期75-80,共6页
Building Electricity
关键词
供电改造
负荷估算
变压器安装容量
负载率
初装成本
实际用电量
高压进线
供电距离
power supply transformation
load estimation
transformer installation capacity
load factor
initial installation cost
actual power consumption
high voltage incoming line
power supply distance