期刊文献+

绩溪抽水蓄能电站下库导流泄放洞布置方案优化设计 被引量:3

Optimal Design of Layout Scheme of Diversion and Discharge Tunnel at Lower Reservoir of Jixi Pumped Storage Power Station
下载PDF
导出
摘要 针对强风化粗粒花岗岩强度低、成洞条件差的特点,结合绩溪抽水蓄能电站下水库调洪要求,对导流泄放洞布置方案进行优化设计,同时对洪水期发电影响进行了分析,并优选了阀门型式,降低了工程造价。 In view of the characteristics of low strength and poor cave-forming condition of strongly weathered coarse-grained granite,combined with flood regulation requirements of lower reservoir of Jixi pumped storage power station,the layout scheme of diversion and discharge tunnel is optimized and the impact on power generation during the flood season is analyzed.In addition,the valve type is optimized which reduces the project cost.
作者 赵瑞存 ZHAO Ruicun(PowerChina Huadong Engineering Corporation Limited,Hangzhou 311122,China;Pumped Storage Engineering Center of Zhejiang Province,Hangzhou 311122,China)
出处 《西北水电》 2021年第3期53-57,共5页 Northwest Hydropower
关键词 洪水调度 泄流能力 导流泄放洞 套筒阀 flood regulation discharge capacity diversion and discharge tunnel sleeve valve
  • 相关文献

参考文献8

二级参考文献21

  • 1马来西亚巴贡水电站工程CW2标业主.Employer's Requiremerits- Bakun Hydroelectric Project, Package CW2-Main Civil Works, Volume 2 of 7, Books 1 and2 [Z] ,2001. 被引量:1
  • 2严优丽,范建朋,杨建红,等.马来西亚巴贡水电站工程概念设计报告[R].西安:西北勘测设计研究院,2002. 被引量:2
  • 3卞全,陈炀,王康柱.马来西亚巴贡水电站放水孔设计准则[R].西安:西北勘测设计研究院,2004. 被引量:1
  • 4严根华,胡去劣,陈发展.马来西亚巴贡水电站放水孔水工模型试验研究[R].南京:南京水利科学研究院,2005. 被引量:1
  • 5王君利,安盛勋,范建朋,等.放水孔运行条件及有关设计问题[R].西安:西北勘测设计研究院,2005. 被引量:1
  • 6陈炀,罗林,王海峰,等.放水孔设计比较方案报告[R].西安:西北勘测设计研究院,2005. 被引量:1
  • 7张晓莉,刘少斌,卫勇,等.马来西亚巴贡水电站放水孔模型试验研究成果报告[R].西安:西北勘测设计研究院,2007. 被引量:2
  • 8Miller E. The submerged discharge valve[J]. Glenfield Gazette, 1969, 229(2). 被引量:1
  • 9Burgi P H. Hydraulic tests and development of multijet sleeve valves [R]. Bur. Reclam. Rep., 1977. 被引量:1
  • 10卫勇.黄河公伯峡水电站发包设计阶段旋流消能泄洪洞常压水工模型试验报告[R].西安:国家电力公司西北勘测设计研究院工程科研实验院,2002.. 被引量:1

共引文献48

同被引文献28

引证文献3

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部