期刊文献+

“汇众301”铺管起重船托管架系统镗孔工艺研究

Boring Technology of Stinger System of Huizhong 301 Pipelaying Crane Vessel
下载PDF
导出
摘要 随着全球对能源需求不断扩大,海上油气田的开发越来越受到关注,具备铺管作业能力的铺管船已成为海上油气田开发的关键性装备。而作为S形铺管作业的关键装备,托管架铰点的装配精度及功能实现越来越受到重视。我司在建造“汇众301”铺管起重船时制定的托管架系统铰点镗孔工艺,填补了国内的空白,可供其他船厂借鉴。 With the continuous expansion of global energy demand,the development of offshore oil and gas fields has attracted more and more attention,and the pipelaying vessel has become the key equipment for the development of offshore oil and gas fields.As the key equipment of S-type pipelaying operation,the precision and function of the hitch point structure of the stinger have been paid more and more attention.This paper expounds the boring technology of hitch point structure in stinger system of the pipelaying crane vessel“Huizhong 301”built in our company.
作者 黄创贵 聂朋 黄江峰 梁玉鑫 HUANG Chuanggui;NIE Peng;HUANG Jiangfeng;LIANG Yuxin(CSSC Huangpu Wenchong Shipping Co.,Ltd.,Guangzhou 510715)
出处 《广东造船》 2021年第3期80-83,共4页 Guangdong shipbuilding
关键词 铺管起重船 托管架 镗孔工艺 Pipelaying Crane vessel Stinger Boring technology
  • 相关文献

参考文献4

二级参考文献35

  • 1VEER R V. Application of linearized Morison load in pipe lay stinger design[ C ]//Proceedings of the 27th Internation- al Conference on Offshore Mechanics and Arctic Engineer- ing. Estoril, Portugal, 2008:247-256. 被引量:1
  • 2SILVA L D, LIMA H M, JACOB B P. Pipeline-lay barge interaction model for the simulation model for the simulation o:f S-lay installation procedures [ C ]// Proceedings of the 27th International Conference on Offshore Mechanics and Arctic Engineering. Arctic Engineering. Estoril, Portugal, 2008:58487. 被引量:1
  • 3MARTINEZ C E. Laying modeling of submarine pipelines using contact elements into a corotational formulation [ J ]. Journal of Offshore Mechanics and Arctic Engineering Copy- right, 2003, 125 : 145-152. 被引量:1
  • 4JENSEN G A. Modeling and control of offshore marine pipe- line during pipelay[ C]//17th World Congress, Internation- al Federation of Automatic Control. Seoul, Korea, 2008 : 15034-15039. 被引量:1
  • 5SILVA D M L, PEREIRA A C P, JACOB B P. A contact model for the simulation of line collision in offshore oil ex- ploitation[ C]// Proceedings of the XXVIII Latin American Congress on Computational Methods in Engineering Porto, Portugal, 2007:22-35. 被引量:1
  • 6SILVA D M L, CORRI:A F N, JACOB B P. A generalized contact model for nonlinear dynamic analysis of floating off- shore systems[ C l// Proceedings of the 25th International Conference on Offshore Mechanics and Arctic Engineering. Hamburg, Germany, 2006-92155. 被引量:1
  • 7GONG S F, CI-IEN K, CttEN Y, et al. Configuration anal- ysis of deepwater S-lay pipeline[J]. China Ocean Engineer- in,,. 2011.25(3) :519-530. 被引量:1
  • 8UBISCH B V. Station keeping criteria for dynamically po- sitioned vessels[ C]//Marine Technology Society, Dynam-ic Positioning Conference. Houston, 2004:28-30. 被引量:1
  • 9DNV. DNV recommended practice DNV-RP-C25, environ- mental conditions and environmental loads [ S ]. [ S. 1. ] : Det Norske Veritas, 2007. 被引量:1
  • 10LEGRAS J L. Vessel motion based laying criteria for rigid and flexible pipes in deepwater[ C ]//The International So- ciety of Offshore and Polar Engineers (ISOPE). Vancou- ver, Canada, 2008:48-52. 被引量:1

共引文献62