摘要
文章以中泰铁路高架桥节段箱梁施工为载体,研究32.7m双线预制节段箱梁悬挂拼接技术,总结高速铁路高架桥节段箱梁悬挂拼接施工技术经验。
Based on the construction of box girder in section of viaduct of China-Thailand railway,the article studies the hanging splicing technology of box girder in section of precast section of 32.7 meters double-line,and summarizes the construction experience of hanging splicing technology of box girder in section of viaduct of high-speed railway.
作者
刘志战
LIU Zhizhan(China Railway 11 Bureau Group Co.,Ltd.,Wuhan 430061,China)
关键词
架桥机
临时预应力
悬挂拼接
settled
temporary prestress
suspension splice